City Airport

This contract flooring project came to us via Britspace, a module space company. They had transported the Link corridors and Waiting Areas as pods pre-fitted which had twisted slightly en-route to cause creaking underfoot.

We were contracted to uplift and remove existing sheet flooring, re-fix plywood using 50-70mm tungsten self-tapping screws which were able to penetrate the steel structures. We then applied a 3mm coat of F700 fibre reinforced smoothing compound ready to receive the new floor covering.

We supplied and installed over 2000 sqm of Altro Suprima II including 300mm border and 150mm self-cove finished into a capping seal. All works were completed out of hours and around arrival and departure times to cause the least disturbance to the airport.